Solution
The extension of the existing facility on the north site created difficult structural design and logistical challenges. Altus Group was intrinsically involved in the assessment of cost, time and potential delay risks associated with extending over the operational hospital.
The project was completed in mid-2016. It includes 60 inpatient beds, 110 same-day beds, eight operating theatres, two procedure rooms, eight radiation therapy bunkers, a clinical trials unit and overnight accommodation for country patients.